Another job on the 4.5″ Burrell was to replace the injector. The one fitted was very unreliable and would not consistently work at full working pressure.

A new high pressure injector was sourced from R A Barker and the pipework modified to fit. A steam up proved this all to be working as it should from 180psi down to 80psi.

The first picture shows the completed installation with the following pictures the old injector and pipework.